Submit Free Article

Google
Web www.httparticles.com


httparticles.com serves you free to republish and reprint articles from authors around the net.
Partners
 

Latest Article Added

 
buy phentermine online
Introduction of bear market strategies
Overcoming Weight Loss Plateau Using Calorie Shifting Diet
Magento version release 1.1.7
Natural Baby Products: A natural way to promote health and safety of your child
I answer you Trabalho saborosordln o_O70
Holiday Stress Relief
Buy Affordable Wedding Invitations On The Net
Portalul Judetului Bihor
Logo Redesigning for Image Makeover
You rock man Perfect workqpaz !91
How to Use Drugs in Golf
Congratulations Speciale dank voor uw werkckju ..70
Sales Training Courses Can Help You Close More Sales
Recruitment interview skills training outlines the importance of Defining the role
Good recruitment interviewing skills training make recruiting the right person easy.
Interviewing Skills Training Can Help Avoid Staff Turnover
First Impressions Do Count in Customer Service
Top Car Finance Options to get you on the road this winter.
Defining Knowledge Base Software?
Tips On Choosing Your Tattoo Parlor
Home remedies treatment of vitiligo
Designing Your Miami Beach Condo
Get yourself the "Six Sigma Tag" with our specialized training programs!
That is amazing La decisione inattesaksig O_o03
Inside World of Website Designing.
Fantastic Five of Paris
Airsoft Gun
Getting Durable Modern Furniture
Here that it is possible to tell Dank zu Informationdbqp o_O62
Featured Articles
Real Estate Contract Basics

The real estate contract is the most often used, yet little understood tool in the real estate business. Whether you are a rank beginner or seasoned expert, there is no excuse for not knowing and understanding the real estate contract Read on...

Understanding the mortgage market

The mortgage business is a complicated and ever-changing industry. It is important that you understand how the mortgage market works and how the lenders make their profit Read on...

Computers :: Difference Between Calendar Days And Work Days
Don’t people already know this? Well seems like “Not everybody!”

Both seasoned IT entrepreneurs as well as developers make this common mistake. They don’t seem to quite understand the difference between calendar days and work days. So let me ask you this question – “What should be the delivery date of a project starting on October 1st and having an estimated effort of 160 hours?”

A typical calculation goes like this:

160 hrs / 8 hrs per day = 20 days. So, if the project is starting on October 1st, it should all be done on 21st October. Right? Wrong!

Here is what is involved, in understanding the delivery date based on start date and total number of hours that is required to accomplish the task:

Number of Days per Week: This is the number of days for which the office of the developer’s organization is going to be open in a week. It can be any number from 5 – 6. Like some companies are open for half time on Saturday. So, this figure is 5.5 for such an organization.

Number of Hours per Day: This signifies, the number of normal work hours that developer will be working in particular day. Do not take overtime in account because then you will not have any buffer to use should the project slip.

So, based on the above two numbers, if the Number of Days per week is 5 and the number of hours per day is 8 then the developer is going to work 8 hours per day then you will 8 X 5 = 40 hours of work done per week.

This means it will take 4 weeks to get 160 hours of work done. This is an equivalent of 28 calendar days which means that given a project started on 1st October it cannot be completed before 28th October.

Granted, that the above calculation is very simple, but you get the message! In reality, things are more complex because the utilization of hours depends on other factors like Number of resources on the project, Number of parallel tasks, Holidays etc.

Why knowing this is important?

Knowing this is very important for two very important reasons:

1. It forces you to plan in advance. As you try to think about delivery dates, you automatically begin thinking about the things that affect it.

2. It prevents unnecessary dissatisfaction. Had you not known this, the delivery on October 28th would haven perceived as a 25% slippage in project deadline whereas the developer has been able to meet the deadline.

Author Info:

Mukul Gupta is the CMO of Indus Net Technologies, an India based Internet Consulting firm which specializes in Opensource solutions. You can reach him at script@script2please.com or visit http://www.script2please.com

News Feeds
The purchase of recreational vehicles should not be done on a whim.
The purchase of recreational vehicles should not be done on a whim.

How to Choose a Trade Data Provider
How to Choose a Trade Data Provider

Celica Marketing
Celica Marketing

Lean Six Sigma Consultancy: The Ultimate destiny in your quest for flawless Quality!!
Lean Six Sigma Consultancy: The Ultimate destiny in your quest for flawless Quality!!

Throw Your Special Event with Help of Event Planning Companies
Throw Your Special Event with Help of Event Planning Companies

Labeled articles for your Adsense Site!
Labeled articles for your Adsense Site!

10 Ways to Cut Costs Without Having to Cut People From Your Payroll
10 Ways to Cut Costs Without Having to Cut People From Your Payroll

Management: 6 Essentials of Managing People
Management: 6 Essentials of Managing People

How Gantt Charts Can Help Avoid Disaster
How Gantt Charts Can Help Avoid Disaster

Management: 5 Reasons Why You Must Manage Others Effectively
Management: 5 Reasons Why You Must Manage Others Effectively


Make Your Own Website


Copyright © httparticles.com  2005. All Rights Reserved.